Public bid analysis

Mason PUD 1 Eldon to Duckabush Reconductor

Mason County PUD No. 1

Open — bids due Oct 30, 2026.

This bid set was run through DeadFront.AI's specification analyzer. Below is the auto-generated bid brief, the highest-risk contract provisions we flagged, and the submittal count — the same output an estimator gets inside the app.

Bid Brief

BID LOGISTICS

  • Bid due date/time: 10:00 a.m., Friday, October 30, 2026 — filed with Engineering Manager Jeremiah Waugh at the District's office in Shelton, WA. Late bids will not be considered or accepted; District's internal server is the official clock.
  • Submission format: One (1) signed hard copy of the bid form (original ink or approved e-signature), sealed in packaging clearly marked with bidder's name and address. All responses must be complete and accurate.
  • Bid opening: 10:15 a.m., October 30, 2026 via Zoom (https://us02web.zoom.us/j/83947997681).
  • Mandatory pre-bid meeting: Tuesday, October 6, 2026, 10:00 a.m. PST — MANDATORY. Meet at PUD 1 office, then drive to site.
  • Bid bond: Certified check, cashier's check, or bid bond (WA-licensed surety), not less than 5% of bid amount. No bid considered without it.
  • Performance/Payment bond: 100% of total Project value, per Chapter 39 RCW, payable to Mason County PUD No. 1 (sample form in RFP).
  • Prevailing wage: This is a Prevailing Wage project (RCW 39.12). Rates per L&I published September 21, 2026. Statement of Intent to Pay Prevailing Wages required for contractor AND all subcontractors; Affidavit of Wages Paid required before final payment/retainage release. Certified payroll sent electronically to Katie Arnold (karnold@mason-pud1.org).
  • Union requirement: Not explicitly required, but bidders must employ qualified journeyman-level line workers and corresponding crew.
  • Required bid packet contents: (A) signed bid form; (B) acknowledgment of addenda receipt; (C) bid bond or certified check; (D) signed Certification of Compliance with Wage Payment Statutes; (E) signed Non-Collusion Affidavit; (F) signed A1 Certification Regarding Lobbying; Bidder Information form (incl. Contractor Registration No., UBI No.); RCW 39.30.060 subcontractor listing (HVAC/Plumbing/Electrical, if applicable); Bidder's Data (Total Bid Amount, Trench Safety Systems cost).
  • RFIs/questions: Technical questions to Emily Novotny, PE (719-588-4358, enovotny@tothassociates.com), cc Kristin Masteller and Jeremiah Waugh. Written clarification requests cut off 3:30 p.m., October 16, 2026. Oral statements not binding.

PROJECT SCOPE

Mason County PUD No. 1 is replacing aged/undersized poles and upgrading ~5 miles of overhead conductor to 336 ACSR-Merlin (phase) and 4/0 ACSR-Penguin (neutral) along U.S. Highway 101, from Eldon (MP 319.55) to the Duckabush Recreation Area/Handley Ln (MP 314.5). Work spans Jefferson and Mason Counties.

CRITICAL DEADLINES & MILESTONES

  • Prequalification application due: 3:30 p.m., October 16, 2026
  • Addenda question cutoff: 3:30 p.m., October 16, 2026
  • Final addenda issued: October 20, 2026
  • Bids due: October 30, 2026, 10:00 a.m.
  • Bid award (anticipated): November 10, 2026
  • Notice to Proceed (anticipated): November 13, 2026
  • Contract execution: within 10 days of notice of award
  • Subcontractor identification: within 14 days of contract award
  • Progress Schedule submittal: within 14 days of contract execution
  • Substantial Completion: May 31, 2027 (work must run consecutive weeks — no de-mob/mob)
  • Final Completion: 10 days after Substantial Completion

HIGH-RISK ITEMS & UNUSUAL TERMS

  • Only prequalified contractors may bid — missing the Oct 16 prequalification deadline disqualifies you entirely.
  • Bids disclaiming negligence liability are automatically deemed non-responsive.
  • Only 5 business days' notice required for pre-bid clarification requests before bid opening — tight window, and failure to request clarification binds bidder to Owner's interpretation.
  • Engineer's Estimate: $1,250,000 — useful budget benchmark.
  • Liquidated damages: $500/calendar day beyond Contract Time for missed Substantial Completion.
  • Federal FEMA funding strings attached (Appendix A): EEO, Buy American/domestic preference, Clean Air/Water Act, Byrd Anti-Lobbying, covered telecom equipment prohibition, records access to FEMA/Comptroller General.

KEY FINANCIAL TERMS

  • Retainage: 5% per RCW 60.28, held 45 days after Final Acceptance.
  • Payment: Progress payments monthly; Final Payment due after Final Acceptance.
  • Liquidated damages: $500/day for late Substantial Completion.
  • Change order markup cap: 12% overhead/profit on Contractor/Sub-performed work, 8% on amounts due to Subcontractors.
  • Insurance minimums: $5M CGL, $5M Auto, $5M Employer's Liability.

OWNER-FURNISHED vs CONTRACTOR-FURNISHED

  • Owner: Obtains WSDOT permit and Traffic Control Plan; coordinates outages; performs inspection/final approval.
  • Contractor: Provides ALL materials, labor, clearing, equipment, concrete, fasteners, adhesives, bolts/nuts/washers (non-exhaustive list), utility locates, staging setup/cleanup, erosion control, and as-built documentation.

Top risk items

Highest-scored provisions flagged in the spec set. Routine bid logistics (due date, delivery, forms) are in the brief above. Full rationale and in-PDF citations are available in the app.

  • Risk score 90Request for Payment — Final Release of ClaimsFinal payment constitutes a waiver of all claims by Contractor against the District except unsettled claims specifically identified. Contractor releases the District from all…
  • Risk score 90Article 9 — IndemnificationIndemnification obligation not limited by amount/type of damages under workers' compensation or similar acts for claims by Contractor's/Subcontractor's employees. Contractor…
  • Risk score 90Project Overview — Prequalification DeadlinePrequalification applications must be submitted by 3:30 p.m. on October 16, 2026, to ensure enough time for consideration of the application prior to the bid due date.
  • Risk score 85Request for Payment — Release of Claims upon Progress PaymentUpon payment, Contractor forever releases the District from any and all claims arising under or in connection with the Project during the period covered (except retainage claims),…
  • Risk score 85Article 19 — LitigationParagraphs 19.1, 19.2, 19.5, and 19.6 are conditions precedent to litigation. All unresolved Claims shall be waived and released unless Contractor strictly complies with time…
  • Risk score 80Appendix A — Withholding of PaymentsMason County PUD No. 1 may or, upon written request of the Department of Labor, must withhold accrued payments from the contractor to satisfy unpaid wages, interest, and…
  • Risk score 80Article 9 — IndemnificationContractor shall defend, indemnify and hold harmless Owner and Indemnified Parties from all claims, damages, losses and expenses, direct, indirect, or consequential, including…
  • Risk score 80Article 19 — Notice of ClaimContractor shall submit notice of all Claims to the Owner in writing within seven (7) days of the event giving rise to them, including reasonable description of the event and…
  • Risk score 80QUALIFIED BIDDERS — Qualified BiddersPrequalification applications must be submitted by 3:30 p.m. on October 16, 2026, to ensure enough time for consideration prior to the bid due date.
  • Risk score 80RESPONSE EVALUATION — Response EvaluationBids conditioned upon different terms shall be rejected as non-responsive. Any bid which attempts to disclaim liability for the Bidder's negligence or disclaim liability for…

4 submittals

Auto-built from the specifications with CSI section, submittal type, and long-lead flags. The full submittal log (with Excel export) is available in the app.

Source: agency's published bid documents. View source documents

Analyzed from the bid set (v1).

Bidding this project? Get the full analysis

See every flagged provision with citations, the complete submittal log, and document chat across the whole bid set.