Benton PUD Padmount Switchgear PME-11 & 12 (26-21-15)
Benton County PUD No. 1
Bid closed Aug 5, 2026 — kept as a sample of DeadFront output.
This bid set was run through DeadFront.AI's specification analyzer. Below is the auto-generated bid brief and the highest-risk contract provisions we flagged — the same output an estimator gets inside the app.
Bid Brief
This is a supply/equipment procurement (not a construction bid) for padmount switchgear — no construction labor, prevailing wage, or pre-bid meeting requirements apply here.
BID LOGISTICS
- Due date/time: Wednesday, August 5, 2026 at 3:00 PM PST
- Submission location: Public Utility District No. 1 of Benton County, Procurement Department, 2721 W. 10th Avenue, Kennewick, WA 99336 (mail to PO Box 6270, Kennewick, WA 99336, Attn: Procurement Dept, Bid #26-21-15)
- Format: SEALED bids required. No electronic submission format specified. District assumes NO responsibility for bids not physically received by deadline — no postmark/courier exception.
- Mandatory pre-bid meeting: Not found in documents (none referenced — this is a materials bid, not construction)
- Bid bond: Certified/cashier's check OR Bid Bond, not less than 5% of bid amount, corporate Surety licensed in WA (RCW 54.04.080)
- Performance bond: 100% of contract price required from successful bidder, before contract becomes binding on District
- Prevailing wage/union/certified payroll: Not found in documents
- Required bid packet contents: Completed Bid Schedule (unit price, total, tariff disclosure per item); tariff classification/duty rate/country-of-origin disclosure if tariff charged; delivery schedule; warranty statement; Firm Price YES/NO declaration (with pricing methodology/index if not firm); exceptions to Exhibit A (Specs) YES/NO; exceptions to Exhibit B (Sample Contract/Bond) YES/NO; addenda acknowledgment; manufacturer/country of origin; supplier name, address, email, phone; signature block with title/date; WA Contractor's Registration No.; Tax ID No.
- Questions/RFIs: Submit to cp@bentonpud.org; extension requests due July 21, 2026 by 3:00 PM PST; Addendum issued July 22, 2026
PROJECT SCOPE
Supply of padmount deadfront switchgear for Benton PUD: 6 units of PME-11 (15kV, #65162R1-S399) and 2 units of PME-12 (15kV, #65172R1-E397), both per BPUD Spec #2011-01, with 3093 end fittings and stainless steel nameplates. This is equipment procurement, not installation.
CRITICAL DEADLINES & MILESTONES
- Bid issued: July 15, 2026
- Extension request deadline: July 21, 2026, 3:00 PM PST
- Addendum issued: July 22, 2026
- Bid due: August 5, 2026, 3:00 PM PST
- Bid award date: August 25, 2026
- Contract execution + performance bond due: within 10 days of award notification (or 5% bid bond forfeited)
HIGH-RISK ITEMS & UNUSUAL TERMS
- No post-bid corrections allowed — any error in your bid is locked in once submitted
- District has sole discretion to deem modifications/exceptions "material" and reject bid as non-responsive
- Undisclosed tariffs are non-reimbursable — must disclose tariff classification, duty rate, and country-of-origin at bid time or eat the cost later
- District can split line items between vendors based on delivery speed — don't assume full award of quantity bid
- Broad right to reject any/all bids with no stated criteria
- Bidder pays own legal costs to protect confidential info from public records disclosure
KEY FINANCIAL TERMS
- Payment due within 30 days of acceptance or valid invoice, whichever is later
- Pricing must exclude Federal Excise Tax; WA State Sales Tax applies but excluded from bid price
- 5% bid bond forfeited as liquidated damages if contract/bond not executed within 10 days of award notice
- Firm pricing preferred; tariff cost adjustments only negotiable in good faith if tied to documented regulatory/law changes — general market/supply chain issues don't qualify
OWNER-FURNISHED vs CONTRACTOR-FURNISHED
Not found in documents — this bid is 100% contractor/vendor-furnished equipment (switchgear units); no owner-furnished materials referenced.
Top risk items
Highest-scored provisions flagged in the spec set. Routine bid logistics (due date, delivery, forms) are in the brief above. Full rationale and in-PDF citations are available in the app.
- Risk score 80General Instructions to Bidder — Liquidated Damages for Bond FailureIn the event the successful bidder fails to furnish an approved Performance Bond and sign the contract within ten (10) days after notification by the District, an amount equal to…
- Risk score 80Exhibit B — PERFORMANCE BONDThe Contractor and surety shall indemnify and save harmless the District, its officers, and agents, from any and all claims, actions or damage of every kind and description…
- Risk score 80Special Instructions to Bidder — Award Purchase Order Tariff TermsAny tariff charges not disclosed at the time of award will not be eligible for reimbursement under this purchase order. Pricing will be considered fixed and not subject to…
- Risk score 75Special Instructions to Bidder — Tariff Price Adjustment LimitationsIf tariff charges are included in the unit price, such charges will be considered fixed for the duration of the purchase order and shall not be subject to adjustment after award,…
- Risk score 70Special Instructions to Bidder — Confidentiality Protection BurdenIn the event the District receives a public records request or other legal process requesting disclosure of information submitted by bidder, the District's sole obligation shall…
Source: agency's published bid documents. View source documents
Analyzed from the bid set (v1).
Bidding this project? Get the full analysis
See every flagged provision with citations, the complete submittal log, and document chat across the whole bid set.
Get the weekly Northwest bid digest
New public-works electrical and utility bids across WA, ID, OR, and MT — each with an AI mini-brief of due dates, bonds, and gotchas. Free, every Monday, unsubscribe anytime.